Lyceum Development Update - July 2024

05
Jul

We are pleased to share the latest developments in the construction of The Lyceum. The steel erection for phases one and two has been fully completed, marking a significant milestone in our project and providing a solid foundation for the upcoming phases.

Phase three is set to commence shortly, right on schedule according to our project timeline, and we are excited to continue our progress and move forward with the next stage of construction.

In addition, the crane from Bastion Point has arrived on site. This crucial piece of equipment will assist our team in maintaining the momentum of our progress, ensuring we meet our upcoming goals efficiently. The transfer deck pour has been successfully completed, which is a key step in the building’s development. This enhances the structural integrity and sets the stage for subsequent construction activities.

Stud welding is well underway and is currently ahead of schedule, which is excellent news for everyone involved as it helps streamline our workflow and keep the project on track. The steel decking for phase one is now 100% complete. This accomplishment not only highlights our team’s hard work but also provides more space and flexibility as we transition to the next section of the site’s evolution.

Stay tuned for more updates as we continue to make significant strides in the development of The Lyceum. Thank you for your continued support and interest in this important piece of Manchester’s history.

Watch the video update here.

CONTACT US

We'd love to hear from you! Please get in touch using our online contact form below and we'll reply as soon as possible.

Thank you! Your submission has been received!
Oops! Something went wrong while submitting the form.
Web design by Metabrand

Head Office

Dubai Office

Contact us

T: +44 (0)151 433 5818
Complaints

Follow IPG