Central Point Development update - April 2024

25
APR

Hello investors,

I am delighted to present the April update from our remarkable Central Point Development project. I am pleased to announce that our excavation works have reached an impressive 90% completion milestone. This pivotal phase has witnessed remarkable progress, thanks to the dedication and hard work of our team on the ground.

 In parallel with the excavation, our substructure works have also progressed significantly, now standing at an impressive 90% completion rate. This phase is crucial in establishing the foundation for the structural integrity of CentralPoint, and I commend everyone involved for their tireless efforts.

 Our team has been making excellent progress in constructing the core walls below ground level. Currently, the bases and walls have reached a depth of 3.5meters, marking an 80% completion rate.

Another significant milestone we have achieved is the completion of the concrete ring beam atop the core walls.This critical element plays a vital role in accommodating brickwork and reinforced concrete planks for the floor slab. I am pleased to report that thiscomponent is now 80% complete, showcasing our attention to detail and quality craftsmanship.

 As we move forward, let us continue to maintain our momentum and dedication to excellence. The progress we have made so far is a testament to our collective effort and commitment to delivering a project of the highest standards.

Watch the full update here.

CONTACT US

We'd love to hear from you! Please get in touch using our online contact form below and we'll reply as soon as possible.

Thank you! Your submission has been received!
Oops! Something went wrong while submitting the form.
Web design by Metabrand

Head Office

Dubai Office

Contact us

T: +44 (0)151 433 5818
Complaints

Follow IPG